To date, the specialists of “Rosseti Novosibirsk” (OJSC “RES”) have already removed the 10 kV power line from the territory of the residential building to ensure the safety of the population. And in order to improve the quality and reliability of electricity supply to local residents, they updated about 1,250 m of overhead power lines. During the construction of new power lines, reinforced concrete supports were installed and insulated wire was installed, as well as sectional disconnectors were installed.
One of the difficult stages of the reconstruction was the replacement of the first support of the transition of the cable part of the line to the overhead one at the point of passage through the Izdreva River. This section is difficult to access – a swampy area between the railway and the river, where the use of special equipment is necessary.
In July, the energy industry will install a transformer substation that will take over part of the load from the village’s existing energy facilities. By the end of the summer, specialists will carry out dismantling and commissioning works, and already at the beginning of autumn, local residents and other consumers of electricity will notice a significant improvement in its quality.
The total amount of investment of “Rosseti Novosibirsk” in the reconstruction of power grids of Goose Brod reached 4,700,000 rubles. But this is far from the only investment project of the company aimed at increasing the reliability and quality of electricity supply to current consumers, as well as ensuring the possibility of connecting to new power grids. In the course of 2024, the energy industry plans to commission more than 450 km of transmission lines and 270 MVA of power in the territory of the Novosibirsk region.